不锈钢电梯门套的生产流程
1、根据设计图纸检查门的规格、测量尺寸等。
1. Check the specifications, measurement dimensions, etc. of the door according to the design drawings.
2、用卷尺量门洞的高与宽,需木龙骨回填大小尺寸,左右位置,并详细标明。
2. Measure the height and width of the door opening with a tape measure, and fill the wooden keel with dimensions, left and right positions, and indicate them in detail.
3、测量位置线,确定木龙骨的位置,用墨斗弹拉出垂直线,一侧门洞两条垂直线。
3. Measure the position line, determine the position of the wooden keel, use an ink fountain to pull out a vertical line, and draw two vertical lines on one side of the door opening.
4、在垂直线上用冲击钻打眼,孔眼与孔眼之间的距离约为30cm,一侧门两排共10个孔眼。冲击钻的钻头应为12mm,所钻孔眼约为6cm。
4. Drill holes with an impact drill on the vertical line, with a distance of about 30cm between each hole. There are a total of 10 holes in two rows on one side of the door. The drill bit of the impact drill should be 12mm, and the drilled hole should be about 6cm.
5、将小木楔用铁锤逐个钉入孔眼,以便固定龙骨板。小木楔的体积大小为5cm×1.5cm×1.5cm,以落叶松制作的为好,因为落叶松的木质结构紧,不容易松动。
5. Nail the small wooden wedges into the holes one by one with a hammer to fix the keel board. The volume size of the small wooden wedge is 5cm × 1.5cm × 1.5cm, and it is better to make it from larch because the wood structure of larch is tight and not easy to loosen.
6、开料制作门框。左右做两侧门框龙骨的木工板门框顶龙骨的木工将高密度九厘板涂胶粘在龙骨上,再用钉子固定。
6. Cutting materials to make door frames. The carpenter who makes the door frame keel on both sides of the door frame will apply glue to the high-density 9cm board and stick it to the keel, and then fix it with nails.
7、将制作好的三条门框按门的形状连接起来,并且用大钉子在接合处固定。
7. Connect the three pre made door frames according to the shape of the door and fix them at the joint with large nails.
8、用刨子将连接好的门框表面修平整,修整边角,棱角分明。
8. Use a planer to smooth the surface of the connected door frame, trim the edges and corners, and make them sharp and angular.
9、将门框放到门洞上,按墙面的水平线为准,门框下拿木头或者砖头垫起,调节门框的高度。下面预留5cm埋在地板的龙骨中。
9. Place the door frame on the doorway, aligning it with the horizontal line of the wall. Use wood or bricks to support the frame and adjust its height. Reserve 5cm below to be buried in the keel of the floor.
10、在门框的上面钉一个钉子,把线垂挂上,通过线垂来调整门框的垂直(也可根据电梯小门框的水平垂直),一边衡量一边用麻花钉将门框固定在门洞墙上。
10. Nail a nail on the door frame, hang the line vertically, adjust the verticality of the door frame through the line verticality (also according to the level and verticality of the elevator small door frame), and use Fried Dough Twists nails to fix the door frame on the door opening wall while measuring.
11、按照甲方要求,刷三到五遍防火涂料(甲方未要求可以不做)
11. According to the requirements of Party A, apply three to five coats of fireproof coating (if not requested by Party A, it can be omitted)
12、测量准确的龙骨回填尺寸,按照测量尺寸下料不锈钢,等待防火涂层干透。
12. Measure the accurate size of the keel backfill, cut stainless steel according to the measured size, and wait for the fireproof coating to dry completely.
13、不锈钢进场后按照标准尺寸和不锈钢所在位置,一一对应放到门洞位置,切不可乱拿。
13. After the stainless steel enters the site, it should be placed in the door opening position according to the standard size and location of the stainless steel, and must not be taken randomly.
14、刷胶水,待胶水处于似粘非粘状态时,粘贴不锈钢。务必一次性安装到位,贴上之后不能拿下,并且拍实,防止后期起鼓分层。
14. Brush the glue, and when the glue is in a non stick state, stick the stainless steel. Be sure to install it in place at once, do not remove it after pasting, and press it firmly to prevent later bulging and layering.
15.电梯门套全部安装完成后,用泡沫护角将它包裹起来,这样能避免受到碰撞损坏。
15. After all elevator door jambs are installed, wrap them with foam corner protectors to avoid collision damage.